cover photo

Linde Gas

We provided a complete solution for Linde Gas, designing, manufacturing, and delivering a custom-built adsorbed KCA vessel. Our collaborative approach, engineering expertise, and logistics management ensured the vessel met Linde's exact requirements and arrived safely on-site.

Client

Linde Gas

Date

May 31, 2018

Services

Manufacture and Delivery

Website

Linde Gas

Project Details

Tech Specs
  • Equipment: Adsorbed KCA vessel
  • Certification: GOST
  • Materials: P 355 NL
  • Weight: 72,600 kg
Project Timeline
  • Materials Lead Time: 5 weeks (ensuring efficient material procurement)
  • Production Design Time: 3 weeks (streamlined design process)
  • Production Time: 5 weeks (efficient manufacturing processes)
  • Logistic Time: 3 weeks (timely delivery to meet project deadlines)